Central · Municipal utility tunnels

Pipe-jacking loss response in Central China: plugged in 2 hours

Slurry suddenly escaped during pipe jacking for a utility tunnel in Central China. It drained along a cover channel, surface settlement hit 30 mm and kept growing, endangering a nearby gas line.

Project overview

Region
Central
Project type
Municipal utility tunnels
Project scale
A utility-tunnel jacking section with 30 mm ground settlement beside a gas main

Construction challenges

The main construction challenges encountered on this project.

Challenge 1Hidden leak

The loss channel ran under the cover — its location could not be seen directly.

Challenge 2Growing settlement

Settlement reached 30 mm and kept developing, risking deformation of the nearby line.

Challenge 3No long stop

The tunnel is a regional power route — downtime ripples to users.


Solution & materials

Materials and mix ratios used step by step on this project, for reference by similar works.

StageMaterialFunctionRatio / dosage
PlugRapid-set plugging agentSeal the leak fastTrial-mixed per leak
Wall protectionPAM-S concentrated slurryRe-film and restore1:200
PressureBENT-N thick slurryBackfill, steady pressure10%–12%
MonitorSettlement monitoringTrack settlement & returnsEvery 2 hours

Implementation notes

Following the emergency plan, crews plugged the leak with a rapid-set agent, re-filmed the wall with 1:200 PAM-S concentrate, backfilled with thick slurry to steady pressure and intensified settlement monitoring. The leak stopped within 2 hours, settlement converged, and jacking resumed 3 days later with no secondary collapse.


Delivered results

2 hours
Time to plug
3 days
Earlier resumption
How results were verifiedGround settlement monitoring plus plugging and recovery timeline records


Related products

GET A QUOTE

Tell us your strata conditions —
get tailored selection advice

Share your strata, borehole diameter and schedule; engineers will reply with mix advice, quantity estimates and lead time. Your information is used only for this enquiry.

✓On-site strata compatibility assessment (per project arrangement)
✓Batch test report & certificate with every shipment
✓On-site mix commissioning by our engineers (per project arrangement)
✓Samples and product brochures on request
Sales hotline
Business email
Form mode
For a quick conversation, leave your name, phone and a short message. Choose detailed project requirements if you have strata, borehole diameter or schedule data.
Filled in from the entry point you used; you can change it
Additional strata (multiple choices)
We will contact you to discuss your requirements.